Echelon LCY10

Echelon LCY10 is a major data centre located in the Docklands area of London,
providing an IT load capacity of 17MW across nine data halls.

2022 / 2025

T Clarke

Docklands, London

About ENVIRO

Project Overview

Echelon LCY10 is a major data centre located in the Docklands area of London, providing an IT load capacity of 17MW across nine data halls.

The facility has been designed to support extensive computing, data storage and network infrastructure, with a 12,000 sq m footprint providing space for both current and future operational requirements. The development also includes 1,200 sq m of office space to support on-site administrative and operational teams.

As a technically complex data centre environment, the project required detailed commissioning management, controlled testing and close coordination across all MEP services.

Project

Echelon LCY10 2022- 2025

Sector

Data Centre

Delivery Partner

T Clarke

Building Size

12,000 sq m / 129,000 sq ft

Enviro Role

Hybrid CxM / MEP commissioning management

Data Halls

9

Project Type

Data centre construction and phased handover

Key Focus

MEP commissioning, integrated testing, heat-load testing and phased handover support

The Challenge

LCY10 presented a complex build and handover environment, with the building not originally designed for phased handovers.

This created a significant commissioning challenge, requiring careful system planning and coordination to allow areas of the facility to be handed over in phases while maintaining performance across live data halls.

The project demanded a flexible and technically controlled approach, particularly around system amendments, heat-load testing, integrated system testing and the management of live operational performance during each phase of progression.

Enviro Scope
of Work

ENVIRO was contracted to provide MEP commissioning management and validation services for the project close-out phase.

The scope included managing commissioning activity across 24/7 shift patterns, supporting remedial water treatment, maintaining continued water management through to floor close-out, driving HVAC balancing teams to completion and ensuring commissioning documentation was reviewed, approved and signed off.

What We Offer

Our Approach

Employed by T Clarke, ENVIRO acted as a hybrid CxM and MEP commissioning management partner throughout the project. Working closely with the T Clarke team, ENVIRO helped design and implement multiple system amendments to enable phased handovers. This included ensuring that, at each stage of progression, the live side of the data halls continued to maintain performance.

ENVIRO and T Clarke also authored commissioning and test scripts from Level 1 through to Level 5, with ENVIRO leading from the front during test progressions. The project required a sustained team effort, with extended working periods and weekend activity forming part of the delivery process.

  • 01

    Validate

    Verifying the current condition of mechanical systems on site.

  • 02

    Coordinate

    Aligning outstanding commissioning actions with the wider project team.

  • 03

    Support

    Driving remedial works and progress across active work areas.

  • 04

    Document

    Maintaining clear documentation control through to handover.

Key Services Delivered

Hybrid CxM support

MEP commissioning management

Phased handover strategy support

System amendment coordination

Level 1 to Level 5 test script authoring

Heat-load testing management

Integrated system testing

Live data hall performance monitoring support

Commissioning coordination across all MEP services

Testing progression leadership

Handover support

Objective

The requirement to introduce phased handovers into a building not originally designed for that approach made LCY10 a highly technical and coordination-heavy project.

ENVIRO’s role extended beyond standard commissioning management, supporting the wider team in adapting system strategies, coordinating test progression and maintaining operational performance across live environments.

This level of involvement was particularly important given the critical nature of data centre infrastructure, where system resilience, performance and continuity are central to successful delivery.

Electrical & Mechanical Infrastructure

Phoenix Mechanical Electrical delivered a comprehensive electrical services installation to support the operational demands of 21 Moorfields. This included small power, general power, UPS and lighting distribution boards, with dual supplies provided to key trader floors.

The wider installation included LV and MV fit out and distribution, general switchgear, base build MV supply, earthing and bonding, lighting control systems, general and emergency lighting, high-level power and cleaners’ circuits.

ENVIRO’s role focused on supporting the commissioning management, validation and close-out of MEP systems to help ensure the building could progress towards successful handover.

Results

ENVIRO supported T Clarke through a complex data centre commissioning and handover process, helping to create a workable phased handover strategy for LCY10.

Through close collaboration, technical coordination and hands-on commissioning management, ENVIRO helped manage all MEP services, lead test progressions and support live data hall performance throughout each stage of delivery.

The project required significant commitment across the full team, with the successful progression of testing and handover activity reflecting the strength of the partnership between ENVIRO and T Clarke.

Systems managed by ENVIRO

All MEP services

Heat-load testing

Integrated system testing

Cause and Effect management

Deliver your next project
with confidence

ENVIRO provides specialist commissioning management and validation support for complex
construction projects, helping teams manage risk, maintain compliance and keep progress moving.