A&O Shearman is relocating its London headquarters from One Bishops’ Square to 2 Broadgate,
a major commercial development on the Broadgate campus near Liverpool Street Station.
A&O Shearman is relocating its London headquarters from One Bishops’ Square to 2 Broadgate, a major commercial development on the Broadgate campus near Liverpool Street Station. The firm has signed a lease to occupy 354,000 sq ft of environmentally conscious workspace,with a phased move planned across winter 2026 and early 2027.
The new headquarters will reduce the firm’s footprint from almost 500,000 sq ft, creating a more agile, high-tech and open-plan working environment. Located next to Liverpool Street Station and the Elizabeth Line, the project represents a major corporate relocation within one of London’s most connected commercial districts.
A&O Shearman London Headquarters Relocation, 2025 - August 2026
Commercial / Legal / Corporate Office
MCS
354,000 sq ft
Mechanical commissioning management
BG/29/21 management, BS 8558 management
Major office relocation and fit out
High End Commercial Fit Out
BREEAM Excellent, LEED v3 Gold
A&O Shearman
The scale and profile of the relocation required a structured commissioning management approach to support programme certainty, technical compliance and system performance. With a high-quality office environment, data room heat-load requirements, domestic water compliance obligations and multiple mechanical systems requiring coordination, the project demanded clear management, robust documentation and close control of commissioning activity.
ENVIRO was appointed to provide mechanical commissioning management services, helping to coordinate key commissioning activities and support the project team through critical stages of delivery.
ENVIRO was contracted to provide MEP commissioning management and validation services for the project close-out phase.
The scope included managing commissioning activity across 24/7 shift patterns, supporting remedial water treatment, maintaining continued water management through to floor close-out, driving HVAC balancing teams to completion and ensuring commissioning documentation was reviewed, approved and signed off.
Employed by MCS, ENVIRO provided mechanical commissioning management support across key building services packages. The team focused on ensuring commissioning activity was properly planned, coordinated, managed and documented in line with project requirements.
This included BG/29/21 management, HVAC commissioning management, ductwork cleaning management, heat-load test authoring and management, and BS 8558 management for domestic water systems. ENVIRO also supported chlorination and domestic water performance testing, helping to ensure systems were progressed in a controlled and compliant manner.
Verifying the current condition of mechanical systems on site.
Aligning outstanding commissioning actions with the wider project team.
Driving remedial works and progress across active work areas.
Maintaining clear documentation control through to handover.
The project forms part of A&O Shearman’s move towards a more efficient and future-focused workplace.
The new 2 Broadgate headquarters will provide a modern working environment designed around agility, technology and collaboration, while reducing the firm’s overall occupied footprint.
ENVIRO’s commissioning management role supports the technical delivery of this transition, ensuring key mechanical systems are properly managed, tested and validated.
Phoenix Mechanical Electrical delivered a comprehensive electrical services installation to support the operational demands of 21 Moorfields. This included small power, general power, UPS and lighting distribution boards, with dual supplies provided to key trader floors.
The wider installation included LV and MV fit out and distribution, general switchgear, base build MV supply, earthing and bonding, lighting control systems, general and emergency lighting, high-level power and cleaners’ circuits.
ENVIRO’s role focused on supporting the commissioning management, validation and close-out of MEP systems to help ensure the building could progress towards successful handover.