Echelon LCY10 is a major data centre located in the Docklands area of London, providing an IT load capacity of 17MW across nine data halls.
The facility has been designed to support extensive computing, data storage and network infrastructure, with a 12,000 sq m footprint providing space for both current and future operational requirements. The development also includes 1,200 sq m of office space to support on-site administrative and operational teams.
As a technically complex data centre environment, the project required detailed commissioning management, controlled testing and close coordination across all MEP services.
Echelon LCY10 2022- 2025
Data Centre
T Clarke
12,000 sq m / 129,000 sq ft
Hybrid CxM / MEP commissioning management
9
Data centre construction and phased handover
MEP commissioning, integrated testing, heat-load testing and phased handover support
LCY10 presented a complex build and handover environment, with the building not originally designed for phased handovers.
This created a significant commissioning challenge, requiring careful system planning and coordination to allow areas of the facility to be handed over in phases while maintaining performance across live data halls.
The project demanded a flexible and technically controlled approach, particularly around system amendments, heat-load testing, integrated system testing and the management of live operational performance during each phase of progression.
ENVIRO was contracted to provide MEP commissioning management and validation services for the project close-out phase.
The scope included managing commissioning activity across 24/7 shift patterns, supporting remedial water treatment, maintaining continued water management through to floor close-out, driving HVAC balancing teams to completion and ensuring commissioning documentation was reviewed, approved and signed off.
Employed by T Clarke, ENVIRO acted as a hybrid CxM and MEP commissioning management partner throughout the project. Working closely with the T Clarke team, ENVIRO helped design and implement multiple system amendments to enable phased handovers. This included ensuring that, at each stage of progression, the live side of the data halls continued to maintain performance.
ENVIRO and T Clarke also authored commissioning and test scripts from Level 1 through to Level 5, with ENVIRO leading from the front during test progressions. The project required a sustained team effort, with extended working periods and weekend activity forming part of the delivery process.
Verifying the current condition of mechanical systems on site.
Aligning outstanding commissioning actions with the wider project team.
Driving remedial works and progress across active work areas.
Maintaining clear documentation control through to handover.
The requirement to introduce phased handovers into a building not originally designed for that approach made LCY10 a highly technical and coordination-heavy project.
ENVIRO’s role extended beyond standard commissioning management, supporting the wider team in adapting system strategies, coordinating test progression and maintaining operational performance across live environments.
This level of involvement was particularly important given the critical nature of data centre infrastructure, where system resilience, performance and continuity are central to successful delivery.
Phoenix Mechanical Electrical delivered a comprehensive electrical services installation to support the operational demands of 21 Moorfields. This included small power, general power, UPS and lighting distribution boards, with dual supplies provided to key trader floors.
The wider installation included LV and MV fit out and distribution, general switchgear, base build MV supply, earthing and bonding, lighting control systems, general and emergency lighting, high-level power and cleaners’ circuits.
ENVIRO’s role focused on supporting the commissioning management, validation and close-out of MEP systems to help ensure the building could progress towards successful handover.
ENVIRO supported T Clarke through a complex data centre commissioning and handover process, helping to create a workable phased handover strategy for LCY10.
Through close collaboration, technical coordination and hands-on commissioning management, ENVIRO helped manage all MEP services, lead test progressions and support live data hall performance throughout each stage of delivery.
The project required significant commitment across the full team, with the successful progression of testing and handover activity reflecting the strength of the partnership between ENVIRO and T Clarke.