Project Overview

A&O Shearman is relocating its London headquarters from One Bishops’ Square to 2 Broadgate, a major commercial development on the Broadgate campus near Liverpool Street Station. The firm has signed a lease to occupy 354,000 sq ft of environmentally conscious workspace,with a phased move planned across winter 2026 and early 2027.

The new headquarters will reduce the firm’s footprint from almost 500,000 sq ft, creating a more agile, high-tech and open-plan working environment. Located next to Liverpool Street Station and the Elizabeth Line, the project represents a major corporate relocation within one of London’s most connected commercial districts.

Project

A&O Shearman London Headquarters Relocation, 2025 - August 2026

Sector

Commercial / Legal / Corporate Office

Delivery Partner

MCS

Building Size

354,000 sq ft

Enviro Role

Mechanical commissioning management

Key Standards/ Compliance

BG/29/21 management, BS 8558 management

Project Type

Major office relocation and fit out

Working Pattern

High End Commercial Fit Out

Sustainability

BREEAM Excellent, LEED v3 Gold

End User

A&O Shearman

The Challenge

The scale and profile of the relocation required a structured commissioning management approach to support programme certainty, technical compliance and system performance. With a high-quality office environment, data room heat-load requirements, domestic water compliance obligations and multiple mechanical systems requiring coordination, the project demanded clear management, robust documentation and close control of commissioning activity.

ENVIRO was appointed to provide mechanical commissioning management services, helping to coordinate key commissioning activities and support the project team through critical stages of delivery.

Enviro Scope
of Work

ENVIRO was contracted to provide MEP commissioning management and validation services for the project close-out phase.

The scope included managing commissioning activity across 24/7 shift patterns, supporting remedial water treatment, maintaining continued water management through to floor close-out, driving HVAC balancing teams to completion and ensuring commissioning documentation was reviewed, approved and signed off.

What We Offer

Our Approach

Employed by MCS, ENVIRO provided mechanical commissioning management support across key building services packages. The team focused on ensuring commissioning activity was properly planned, coordinated, managed and documented in line with project requirements.

This included BG/29/21 management, HVAC commissioning management, ductwork cleaning management, heat-load test authoring and management, and BS 8558 management for domestic water systems. ENVIRO also supported chlorination and domestic water performance testing, helping to ensure systems were progressed in a controlled and compliant manner.

  • 01

    Validate

    Verifying the current condition of mechanical systems on site.

  • 02

    Coordinate

    Aligning outstanding commissioning actions with the wider project team.

  • 03

    Support

    Driving remedial works and progress across active work areas.

  • 04

    Document

    Maintaining clear documentation control through to handover.

Key Services Delivered

Mechanical commissioning management

BG/29/21 management

HVAC commissioning management

Heat-load test authoring and management

Ductwork cleaning management

BS 8558 management

Chlorination management

Domestic water performance testing

Domestic water commissioning and balancing

Coordination of commissioning documentation

Support through phased project delivery

Objective

The project forms part of A&O Shearman’s move towards a more efficient and future-focused workplace.

The new 2 Broadgate headquarters will provide a modern working environment designed around agility, technology and collaboration, while reducing the firm’s overall occupied footprint.

ENVIRO’s commissioning management role supports the technical delivery of this transition, ensuring key mechanical systems are properly managed, tested and validated.

Electrical & Mechanical Infrastructure

Phoenix Mechanical Electrical delivered a comprehensive electrical services installation to support the operational demands of 21 Moorfields. This included small power, general power, UPS and lighting distribution boards, with dual supplies provided to key trader floors.

The wider installation included LV and MV fit out and distribution, general switchgear, base build MV supply, earthing and bonding, lighting control systems, general and emergency lighting, high-level power and cleaners’ circuits.

ENVIRO’s role focused on supporting the commissioning management, validation and close-out of MEP systems to help ensure the building could progress towards successful handover.

Results

ENVIRO provided structured mechanical commissioning management support across a major corporate office relocation project. Through focused management of HVAC commissioning, domestic water testing, heat-load testing, ductwork cleaning and compliance-related activities, ENVIRO helped support the controlled delivery of critical building services packages for the new A&O Shearman headquarters. The appointment provided MCS and the wider project team with specialist

Systems managed by ENVIRO

LTHW

CHW

Critical CHW

Ventilation

CPC water treatment

Domestic water commissioning

Domestic water balancing

Heat load testing of data rooms

Deliver your next project
with confidence

ENVIRO provides specialist commissioning management and validation support
for complex construction projects, helping teams manage risk,
maintain compliance and keep progress moving.

Related Services

Commissioning & Water Treatment

Compliance & Risk Assessments

Commissioning Mgt & Validation Services